Notice: Crane on Spring Street week of 4/22
Read Notice >
At the juncture of innovation, community, and sustainability.

A VISION FOR CAMBRIDGE

An eye to the future

Over the next several years, the building will undergo a complete interior and exterior renovation, starting with internal abatement work and ending with completion of the building core systems and installation of a new facade. Project milestones will be updated below to show status of the project and estimated start and completion dates for each phase of work.

Enabling
Abatement & Demo
Structural Modifications
Building Façade
Building Systems & Interior Finishes
Final Landscaping
Substantial Completion
November 2020 (complete)
April 2022 - September 2022 (complete)
December 2021 – November 2023 (complete)
May 2022 – April 2024
March 2022 - May 2024
Forty Thorndike Cambridge Massachusetts
June 2023 – May 2024
April 2024

Frequently Asked Questions

Q:
What is the scope of this project?
A:

Transformation of a decommissioned 1970s era jail and courthouse previously owned by the State into an innovative mixed-use project.

Q:
What will be the final use of the redeveloped building?
A:

Mixed use, including: 409,000 sf of office/R&D space, 48 units of affordable rental housing, ground floor retail, childcare and community space.

CONNECT WITH THORNDIKE CONSTRUCTION

Sign up here for construction related email updates and notifications right to your inbox. Fields marked with an asterisk (*) are required.

More ways to communicate with us

Call
The project hotline is: (617) 520-4983

Meet
Construction Update Meetings
(Announced on the NEWS + MEETINGS page)

Read
Explore project materials to download and share
(When available on the NEWS + MEETINGS page)

Have a question?

Construction information:
construction@fortythorndike.com
All other information:
info@fortythorndike.com